Current Projects
Crossrail
Integra have been working on the crossrail project since 2007 and have completed the following tasks:
Provision of interim project management services to CRL in respect of Liverpool Street and Bond Street Stations
Provision of project management to Scott Wilson , Framework Design Consultant , for the design phase of crossrail HV Bulk Power system , a £50M scheme to provide non traction power to all stations, portals and shafts as well as tunnel sections.
Provision of project management services to Scott Wilson , Framework Design Consultant for Farringdon station Oversite development, which consisted of a RIBA D design for a 6 storey commercial office development above Farringdon station.
Provision of Procurement and project management services to Crossrail project delivery partner for the Invitation To Tender ( ITT) for Paddington crossrail station. |
click to enlarge |
| |
| |
| Paddington Integrated Project (PIP)
Integra is providing project management and detailed design services to Scott Wilson for the HV power system on the Paddington Integrated Project.
Client : URS / Scott Wilson |
|
| Volker Rail
Integra is proving commercial management services to Volker Rail for London region rail projects. |
|
| One Hyde Park Development
Integra provided technical assurance services to Laing O’Rourke on the One Hyde Park project for the tunnel link from the hotel to Knightsbridge London Underground station.
As part of the exclusive One Hyde Park development, the developer Project Grande (Guernsey) Ltd, through its Principal Contractor, Laing O'Rourke, were required to design and build a new northern entrance to London Underground's Knightsbridge Station. The works involved the construction of a tunnel connection from the existing ticket hall to a new northern entrance stairs situated adjacent to the Mandarin Hotel. This required major concrete works, architectural finishes, a new glazed canopy and extensions to existing Legacy systems. Integra was engaged by Laing O'Rourke to work with the project manager on all London Underground related issues, including approvals, the compliance of the works to LU standards and the acceptance of the final commissioned works by the maintainer and operator. The passageway was successfully opened in December and was well received by London Underground.
Client: Project Grande (Guernsey) Ltd
|
click to enlarge |
Train Depots
Engineering and assurance experience in the delivery of major train depot works. Facilities include train cleaning, maintenance pits, full train lifting roads, power and services upgrades, staff accommodation and signalling.
Much of the work has been within an operating environment, and therefore the interface with both train operators and maintainers has been crucial.
The depot works have been required to support the introduction of new rolling stock whilst still maintaining and decommissioning the existing stock, this resulted in considerable modelling and stabling analysis to ensure the needs of both the new and old stock could be simultaneously fulfilled.
Client: London Underground Ltd
|

click to enlarge |
click to enlarge |
click to enlarge
|
Training
The infrastructure changes as a result of the Thameslink Programme involve substantial remodelling of Farringdon and Blackfriars Underground Stations. In order for staff working on these stations, both in operations and maintenance, to be aware of the new assets and to safely carry out normal and emergency station operations, the impact on LU staff needs to be measured. As there is also interface with Network Rail (NR) and Train Operating Company (TOC) staff, this also needs to be evaluated from an LU perspective.
In order to hand the new assets over to LU for operational and maintenance use Integra are undertaking the following activities;
- Training Needs Analysis (TNA) for LU operational staff and Maintenance staff
- Liaising with LU management, staff representatives and Chief Maintenance Office representatives to manage expectations and ensure smooth transition
- Dependent on the results of the TNA, develop appropriate solutions to meet staff needs, including briefing materials, briefing strategy and sign off of staff.
- Delivery of briefings and accreditation of LU staff to deliver these briefings
- Close out and handover of materials to LU
Client: Network Rail |
click to enlarge |
Previous Projects
Past experience has included world class projects for contractors, infrastructure owners,
developers and design consultancies some of which include:
Wood Lane Tube Station
Construction of the new station in preparation for a major retail development
adjacent to the station.
Client: Westfield |
click to enlarge |
Shepherds Bush Tube Station
The construction of a new station entrance and station extension as well as alterations to the existing station to facilitate the increase in passenger
demand due to the new retail development. Services included management of the technical assurance process and the assurance of the design and construction through a team of specialist Asset Engineers.
Client: Westfield
|
click to enlarge |
| The Channel Tunnel Rail Link |
click to enlarge |
Modernisation and upgrade of the London Tube |
awaiting
image |
| White City Development |
click to enlarge |
|